East Norton Viaduct
This text is replaced by the Flash movie.
East Norton Viaduct
This 13 span Viaduct close to the village of East Norton, Leicestershire measured 190 metres in length ( two football pitches), 12 storey’s in height and had a mass weight of 26,000 tonnes.Apart from the obvious constraints associated with using explosives to demolish structures of this nature, this project had a number of additional Environmental constraints.
For example:
- the risk of contaminating Eye Brook running below
- the management and control of protected species (bats)
- extensive traffic management
Location:
PeterboroughScope:
Explosive demolition and removal of a 600m long, 12 storey’s high structurally unsound brick viaduct.Programme:
20 weeksResources:
Team of 15 operativesExplosive Engineering team
Heavy excavators
Crushing crew
Structural Engineer