Willow Place

This text is replaced by the Flash movie.

Willow Place

Undertaken for Land Securities, this was another technically challenging scheme requiring;
  • Detailed programming
  • Innovative safe systems of work
  • Ability to work within a live shopping centre
  • Onsite technical skills
  • Effective lines of communication
All were crucial to the projects success.

Phase 1

The de-construction of a cinema complex 75m x 40m x 16m above a live multi storey car park positioned some 30 metres above ground level. This presented extensive problems with regard to:
  • Access
  • Water ingress
  • Noise
  • Dust
  • Vibration
because the internal concrete floor slab, would become the roof to shops and restaurants trading below.

Phase 2

The de-construction of a 120m long office block, 6 storeys in height, 25m wide with 50% of the office structure to be demolished by reduction of 5 storeys from above a fully operational Littlewoods Store!

We employed:
  • Extensive temporary and permanent steelwork
  • 10 x the normal public safety factors
  • Vibration free techniques
  • Methods to ensure the 3000 tonnes of material did not puncture the water proof membrane
  • Heavy craneage, remote controlled plant and specialist concrete cutting techniques
  • Methods to work around live services which could not be diverted until week 12 of the 26 week programme
  • Weather proofing to internal floor slabs to act as functional exposed roofs
By re-sequencing our work and managing the contract pro-actively we:
  • Incorporated additional extensive building works
  • Worked 16 weekends without the Client incurring additional cost
  • Achieved final account settlement within 3 weeks of Practical Completion.

Map

Location:

Corby

Scope:

Asbestos, & soft strip removals, structural investigations & reporting, dismantling, demolition, debuild, service disconnection/diversions.

Client:

Land Securities

Programme:

30 weeks

Resources:

Compact plant-mini excavators + bobcats
Larger excavators + 2 ultra high reach excavators
Scaffold + structural steel temporary works
Scaffold encapsulation
1000 tonne crane
40 operatives

Tonnage:

19,000 tonne

Neighbours:

Littlewoods (trading below) open trading square, WH Smiths, Main High Street thoroughfare.